Thursday, May 3, 2018

May 3, 2018

Work bench wasn't wide enough to support the main gear. Extend the table to support the mains. Now we can build and square-up tailwheel. The frame is starting to look like something.

2 hours










May 2, 2018

Wheels and wheel cover installation
The process of getting the wheels ready to go on the axle took several days and lots of mental planning. First the wheels were "trued" by adjusting the spokes. Then tubes and tires were installed and balanced. Lots of time was spent thinking how to mount the wheel covers. In the end the inboard covers and brake drum was mounted with bolts spacers and "thin" nylock nuts.

Studs were made with threaded rod, "thin" nylock nuts were again used on the inside of the hub and nutted on the outside of the hub along with a jam nut. Then the outside wheel cover was placed on over the studs and held with washers and nuts.

Completion day 5/2/18
Total hours 10













May 1, 2018

Initial checking of main wheels and tail wheel before assembly of the main wheels and covers. 





Wednesday, May 2, 2018

May 1, 2018
Brushed all wing strut gussets


Total Time: 1 hour





Saturday, April 28, 2018

April 28, 2018
Completed left upper wing compression struts, drag anti-drag cables. Tiffany heat shrinking cable ends. Upper, center, and lower wing spars complete.

Total Time 2.5 hours




Thursday, April 26, 2018


April 25, 2018
Set right lower wing spar into right side of fuselage just to check fit.






April 25, 2018 

Left and right lower wing spars complete. Left and right lower wing spars set into fuselage wing carry through tubes.  

Total Time 4 hours











Monday, April 16, 2018

April 16, 2018
Completed center top wing section. Squared leading and trailing edge wing spars. Cut compression struts to length and installed. Tensioned and swaged  drag/anti drag cables to tangs.


Total time 3.5 hours






April 2, 2018
Drilled all wing spars and related sleeves. Bolted all drag, and lift tangs with compression strut plugs to upper, lower, and center wing spars. (Make sure all holes are straight and square.)

Total Time: 8 hours





March 21, 2018
Drilled out all wing drag tangs and lift tangs. Painted lift tangs.

Total Time: 3 hours





March 15, 2018 
Wing materials arrive. Breakdown crate.


Total Time:  1hour