Wednesday, March 7, 2018

March 4, 2018
Attached finished Elevator to Horizontal Stab. 

Total Time .5 hours






February 24 2018
Bent tubing to form "elephant ears" on elevator. Made duplicate. Laid out spar and riveted ribs to form elevator. Elevator complete.

Total Time 6 hours












February 22 2018
Cut, drilled, and bent sheet Aluminum to make elevator ribs.

Total Time 2 hours



February 21, 2018
Lay-out of elevator.

Total Time 1.5 hours


February 20, 2018 
Cut, bent, rolled, and riveted all gussets to horizontal stab. Horizontal Stab complete.
 
Total Time 5 hours







February 12, 2018 

Laid out horizontal stab frame. Bent curves to match each side. Jigged, cut, coped, perimeter tubing to form the exterior of the horizontal stab.
Total Time 2.5 hours