February 20, 2018
Cut, bent, rolled, and riveted all gussets to horizontal stab. Horizontal Stab complete.
Total Time 5 hours
February 12, 2018
Laid out horizontal stab frame. Bent curves to match each side. Jigged, cut, coped, perimeter tubing to form the exterior of the horizontal stab. Total Time 2.5 hours
Sunday, February 4, 2018
February 2, 2018
Gear leg bottom caps fabricated. Installed all rivets in second leg. Gear legs complete.
Total Time 3 hours
January 29, 2018
Cut, coped, drilled, and riveted one side of lower plates on landing gear legs, both left and right sides.
Total Time 4 hours
January 28, 2018
Laid out and
jigging of landing gear legs. Initial layout of horizontal stab. Utilizing
4'x16' table to build gear and horizontal stab at the same time. Total Time 3 hours
Saturday, February 3, 2018
January 25, 2018
Making room for horizontal/elevator and gear legs to be built. (Hoisted next to the rudder!)