Monday, April 16, 2018

April 16, 2018
Completed center top wing section. Squared leading and trailing edge wing spars. Cut compression struts to length and installed. Tensioned and swaged  drag/anti drag cables to tangs.


Total time 3.5 hours






April 2, 2018
Drilled all wing spars and related sleeves. Bolted all drag, and lift tangs with compression strut plugs to upper, lower, and center wing spars. (Make sure all holes are straight and square.)

Total Time: 8 hours





March 21, 2018
Drilled out all wing drag tangs and lift tangs. Painted lift tangs.

Total Time: 3 hours





March 15, 2018 
Wing materials arrive. Breakdown crate.


Total Time:  1hour








Wednesday, March 7, 2018

March 4, 2018
Attached finished Elevator to Horizontal Stab. 

Total Time .5 hours






February 24 2018
Bent tubing to form "elephant ears" on elevator. Made duplicate. Laid out spar and riveted ribs to form elevator. Elevator complete.

Total Time 6 hours












February 22 2018
Cut, drilled, and bent sheet Aluminum to make elevator ribs.

Total Time 2 hours